Morgan Stanley Capital Group Inc. v. Public Utility District No. 1 of Snohomish County, Washington

Media Items
Morgan Stanley Capital Group Inc. v. Public Utility District No. 1 of Snohomish County, Washington - Oral Argument
Get Adobe Flash Player
Morgan Stanley Capital Group Inc. v. Public Utility District No. 1 of Snohomish County, Washington - Opinion Announcement
Get Adobe Flash Player
Advocates
Edwin S. Kneedler (on behalf of Respondent Ferc, in support of the Petitioners)
Walter E. Dellinger, III (on behalf of the Petitioners)
Christopher J. Wright (on behalf of Respondents)
Case Basics
Docket No.: 
06-1457
Petitioner: 
Morgan Stanley Capital Group Inc.
Respondent: 
Public Utility District No. 1 of Snohomish County, Washington, et al.
Consolidation: 
Calpine Energy Services, L.P., et al. v. Public Utility District No. 1 of Snohomish County, Washington, et al., No. 06-1462
Opinion: 
554 U.S. ___ (2008)
Location No location information present.

Cite this page
The Oyez Project, Morgan Stanley Capital Group Inc. v. Public Utility District No. 1 of Snohomish County, Washington , 554 U.S. ___ (2008)
available at: (http://oyez.org/cases/2000-2009/2007/2007_06_1457)
Facts of the Case: 

The California Legislature deregulated the power industry in 1996, establishing a so-called “spot market” in which utilities purchased electricity on the day it was needed. Four years later, during an exceptionally hot summer, wholesale electricity prices skyrocketed. In response, several utilities on the Western power grid determined that they could no longer afford the spot market, and instead negotiated less expensive but still inflated long-term contracts with power suppliers. Once the crisis passed, the utilities asked the government to let them change the contracts to reflect newly lowered electricity prices. The government refused, citing a longstanding Supreme Court doctrine presuming that utilities’ contracts are reasonable. The Ninth Circuit ultimately ordered the government to permit the changes.

Question: 

May the government permit utility companies to renegotiate long-term contracts with wholesale energy suppliers and, if so, what circumstances justify renegotiation?

Conclusion: 

Renegotiation is allowed only if the contract poses "serious harm to the public interest." In this case, the Court decided 5-2 (Justices John G. Roberts and Stephen Breyer took no part in the decision) that the Federal Energy Regulatory Commission had failed to make sufficient factual findings in order to determine whether such serious harm could in fact occur. Therefore, the Court sent the case back down to the Ninth Circuit in order to provide an opportunity to revisit these factual findings. Justice Ruth Bader Ginsburg wrote a concurring opinion stating that she believed the Court should have waited to hear the case until all the facts had been uncovered. However, because the case was heard when it was, she felt obliged to agree with the majority's reasoning. Justice John Paul Stevens, joined by Justice David Souter, dissented, arguing that Congress, not the courts, should set the standards regarding the reasonableness of public contracts.

Sponsor